Here you can see recently acquired construction material, apart from 200 bags cement directly procured from Madras Cement Ltd.

Below is the boundary wall waiting for the gates to arrive before we pour concrete in the columns.
The desgin work of sump is complete and agencies for executing the work have been finalized. On 29th Centering and shuttering labors arrived for starting the sump work. Below is the shuttering material. Steel Reinforcement is being prepared. The excavation work is expected to start on 31march.

 Below the PVC coated, GI chain link fence which is ready to be used for boundary wall work on eastern side of temple.