Tuesday, March 15, 2011

I am writing on this blog after a long time... and lots of good news. Things have moved since the last post. Now the entire civil work for the main temple building is complete. The specifications for interiors have been finalised.  Now ground work has started to identify quality sources for procurement and execution.

Curently following work is happening:
1. Boundary Wall and fencing
2. Sthapati work on northern side

We plan to take up the following work in next few weeks
1. Underground fresh water sump for new temple
2. Fixing the main gates

Soon I will post a tentative schedule for completion of interior work.